Dept. of Trans. PROGRESS Serial No. Contract No. 07-355-08-14 09-317704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 99% 09-INY-395-90.9/99.2 Federal Project: 09-INY-395-100.8/113.0 NONE 09-MNO-395-0.0/6.8 Progress payment No. 06 Payment period ending: 12-20-07 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,990,715.48 -1,035,761.04 2.a. Extra Work 1,677.22 673.89 b. Adjustment Comp. 13,167.76 106,198.57 3. Materials on Hand 4. Earned Subject to Retention 5,005,560.46 -928,888.58 5. Mobilization 600,000.00 0.00 6. Total Work Completed 5,605,560.46 7. Deductions 0.00 936,150.38 8. a.Contract Retentions -296,722.45 0.00 b. Unsatisfactory Prog. -94,391.38 92,888.86 c. Reduction after 95% Comp. 9. Total pay to Contractor 5,214,446.63 100,150.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 100,150.66