Dept. of Trans. PROGRESS Serial No. Contract No. 09-329-11-07 09-318104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 88% 09-INY-190-87.6/88.3 Federal Project: SB-P190(12) Progress payment No. 03 Payment period ending: 11-20-09 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 700,218.55 501,944.50 2.a. Extra Work b. Adjustment Comp. -18,105.73 -18,105.73 3. Materials on Hand 4. Earned Subject to Retention 682,112.82 483,838.77 5. Mobilization 29,400.00 1,470.00 6. Total Work Completed 711,512.82 7. Deductions -5,859.38 -5,859.38 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 705,653.44 479,449.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 479,449.39