Dept. of Trans. PROGRESS Serial No. Contract No. 06-142-08-07 09-330504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 72% 09-SBD-127-27.0/35.0 Federal Project: 09-INY-127-46.3/49.4 NONE Progress payment No. 02 Payment period ending: 05-20-06 DON GARCIA EXCAVATING AND PAVING INC P O BOX 7176 SOUTH LAKE TAHOE CA 96158 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 965,607.18 941,782.18 2.a. Extra Work 7,578.33 7,578.33 b. Adjustment Comp. 16,898.18 16,898.18 3. Materials on Hand 4. Earned Subject to Retention 990,083.69 966,258.69 5. Mobilization 6. Total Work Completed 990,083.69 7. Deductions 8. a.Contract Retentions -49,504.18 -47,121.68 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 940,579.51 919,137.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 919,137.01