Dept. of Trans. PROGRESS Serial No. Contract No. 06-205-10-34 09-330604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 68% 09-INY-395-45.4/50.3 Federal Project: 09-INY-395-50.9/52.9 NONE 09-MNO-6-17.5/26.5 Progress payment No. 01 Payment period ending: 07-20-06 INTERNATIONAL SURFACING SYSTEMS P O BOX 4770 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 578,733.16 578,733.16 2.a. Extra Work b. Adjustment Comp. 14,670.25 14,670.25 3. Materials on Hand 4. Earned Subject to Retention 593,403.41 593,403.41 5. Mobilization 6. Total Work Completed 593,403.41 7. Deductions -45,041.20 -45,041.20 8. a.Contract Retentions -29,670.17 -29,670.17 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 518,692.04 518,692.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 518,692.04