Dept. of Trans. PROGRESS Serial No. Contract No. 06-296-09-55 09-334304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 16% 3% 09-MNO-395-52.7/54.9 Federal Project: NONE Progress payment No. 01 Payment period ending: 10-20-06 CROWN FENCE CO 12118 BLOOMFIELD AVENUE SANTA FE SPRINGS CA 90670 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 78,563.60 78,563.60 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 78,563.60 78,563.60 5. Mobilization 6. Total Work Completed 78,563.60 7. Deductions 8. a.Contract Retentions -7,856.36 -7,856.36 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 70,707.24 70,707.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 70,707.24