Dept. of Trans. FINAL Serial No. Contract No. 09-034-14-13 09-336704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 09-MNO-395-50.7/52.8 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-14-08 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,073,839.92 1,875.00 2.a. Extra Work 24,992.72 24,992.72 b. Adjustment Comp. -14,756.77 -14,756.77 3. Materials on Hand 4. Earned Subject to Retention 2,084,075.87 12,110.95 5. Mobilization 6. Total Work Completed 2,084,075.87 7. Deductions -82,000.00 10,000.00 8. a.Contract Retentions -31,491.04 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 31,491.04 0.00 9. Total pay to Contractor 2,002,075.87 22,110.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 22,110.95