Dept. of Trans. PROGRESS Serial No. Contract No. 11-049-06-46 09-347104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 100% 09-MNO-395-106.3/120.4 Federal Project: NONE Progress payment No. 04 Payment period ending: 02-18-11 WEST COAST PAVING AND CHIP SEALING P O BOX 1231 YREKA CA 96097 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 788,419.87 91,821.59 2.a. Extra Work 6,257.29 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 794,677.16 91,821.59 5. Mobilization 6. Total Work Completed 794,677.16 7. Deductions -147,400.05 -900.05 8. a.Contract Retentions b. Unsatisfactory Prog. 0.00 6,995.61 c. Reduction after 95% Comp. 9. Total pay to Contractor 647,277.11 97,917.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 97,917.15