Dept. of Trans. PROGRESS Serial No. Contract No. 18-172-11-14 09-352104 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 33% Location: Federal Project: 09-INY-168-17.5/18.3 ACST-X027(9) 09-INY-395-114.9/116.4 Progress payment No. 004 Payment period ending: 06-14-18 SPECTRUM CONSTRUCTION GROUP INC 32 EDELMAN IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 318,219.39 92,091.34 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 318,219.39 92,091.34 5. Mobilization 181,362.64 60,454.21 6. Total Work Completed 499,582.03 7. Deductions -30,627.72 -208.17 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 468,954.31 152,337.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 152,337.38