Dept. of Trans. PROGRESS Serial No. Contract No. 14-233-08-17 09-353104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 60% 09-MNO-395-R6.9/R9.9 Federal Project: NHP-P395(243) Progress payment No. 02 Payment period ending: 08-20-14 GRANITE CONSTRUCTION COMPANY 3005 JAMES ROAD BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,492,041.08 1,403,956.45 2.a. Extra Work b. Adjustment Comp. -20,000.00 -20,000.00 3. Materials on Hand 4. Earned Subject to Retention 1,472,041.08 1,383,956.45 5. Mobilization 6. Total Work Completed 1,472,041.08 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,472,041.08 1,383,956.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,383,956.45