Dept. of Trans. PROGRESS Serial No. Contract No. 19-078-16-42 09-353204 PROGRESS PAYMENT VOUCHER %complete: %time: 41% 35% Location: Federal Project: 09-INY-190-69.2/69.8 HSST-S190(25) Progress payment No. 002 Payment period ending: 03-20-19 MEYERS EARTHWORK INC PO BOX 493730 REDDING CA 960493730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 635,824.20 613,474.20 2. a. Extra Work 6,850.16 6,850.16 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 642,674.36 620,324.36 5. Mobilization 190,000.00 190,000.00 6. Total Work Completed 832,674.36 7. Deductions -2,214.64 -2,214.64 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 830,459.72 808,109.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 808,109.72