Dept. of Trans. PROGRESS Serial No. Contract No. 14-203-08-23 09-353304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 38% 09-MNO-395-34.1/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 07-20-14 HERBACK GENERAL ENGINEERING 2531 NOWLIN ROAD MINDEN NV 89423 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 517,355.70 112,531.98 2.a. Extra Work 6,908.66 6,908.66 b. Adjustment Comp. -1,050.00 -1,050.00 3. Materials on Hand 4. Earned Subject to Retention 523,214.36 118,390.64 5. Mobilization 27,880.00 1,394.00 6. Total Work Completed 551,094.36 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 551,094.36 119,784.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 119,784.64