Dept. of Trans. PROGRESS Serial No. Contract No. 14-233-08-14 09-353304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 58% 09-MNO-395-34.1/ .0 Federal Project: NONE Progress payment No. 04 Payment period ending: 08-20-14 HERBACK GENERAL ENGINEERING 2531 NOWLIN ROAD MINDEN NV 89423 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 881,529.96 364,174.26 2.a. Extra Work 19,414.88 12,506.22 b. Adjustment Comp. -1,050.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 899,894.84 376,680.48 5. Mobilization 27,880.00 0.00 6. Total Work Completed 927,774.84 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 927,774.84 376,680.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 376,680.48