Dept. of Trans. PROGRESS Serial No. Contract No. 15-236-10-38 09-356004 PROGRESS PAYMENT VOUCHER %complete: %time: 63% 80% Location: Federal Project: 09-MNO-6-0.8/2.4 HSNH-P006(11) Progress payment No. 002 Payment period ending: 08-20-15 GRANITE CONSTRUCTION COMPANY 3005 JAMES ROAD BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 552,768.95 493,026.69 2. a. Extra Work b. Adustment Comp. -7,290.00 -7,290.00 3. Materials on Hand 4. Earned Subject to Retention 545,478.95 485,736.69 5. Mobilization 6. Total Work Completed 545,478.95 7. Deductions -1,143.75 -1,143.75 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 544,335.20 484,592.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 484,592.94