Dept. of Trans. PROGRESS Serial No. Contract No. 15-261-09-28 09-356004 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 83% Location: Federal Project: 09-MNO-6-0.8/2.4 HSNH-P006(11) Progress payment No. 003 Payment period ending: 09-20-15 GRANITE CONSTRUCTION COMPANY 3005 JAMES ROAD BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 865,717.21 312,948.26 2. a. Extra Work b. Adustment Comp. -122,394.30 -115,104.30 3. Materials on Hand 4. Earned Subject to Retention 743,322.91 197,843.96 5. Mobilization 6. Total Work Completed 743,322.91 7. Deductions -22,749.57 -21,605.82 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 720,573.34 176,238.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 176,238.14