Dept. of Trans. PROGRESS Serial No. Contract No. 13-295-09-36 09-357404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 96% 09-MNO-395-1.0/100.0 Federal Project: CSTP-X051(27) Progress payment No. 03 Payment period ending: 10-18-13 GRANITE CONSTRUCTION COMPANY P O BOX 5127 BAKERSFIELD CA 93380 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,283,892.89 252,921.32 2.a. Extra Work 25,045.09 25,045.09 b. Adjustment Comp. -14,522.88 -14,522.88 3. Materials on Hand 4. Earned Subject to Retention 4,294,415.10 263,443.53 5. Mobilization 6. Total Work Completed 4,294,415.10 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,294,415.10 263,443.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 263,443.53