Dept. of Trans. PROGRESS Serial No. Contract No. 13-324-08-33 09-357404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 96% 09-MNO-395-1.0/100.0 Federal Project: CSTP-X051(27) Progress payment No. 04 Payment period ending: 11-20-13 GRANITE CONSTRUCTION COMPANY P O BOX 5127 BAKERSFIELD CA 93380 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,321,173.84 37,280.95 2.a. Extra Work 26,844.54 1,799.45 b. Adjustment Comp. -14,522.88 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,333,495.50 39,080.40 5. Mobilization 6. Total Work Completed 4,333,495.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,333,495.50 39,080.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 39,080.40