Dept. of Trans. PROGRESS Serial No. Contract No. 13-353-08-41 09-357404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 96% 09-MNO-395-1.0/100.0 Federal Project: CSTP-X051(27) Progress payment No. 05 Payment period ending: 02-20-13 GRANITE CONSTRUCTION COMPANY P O BOX 5127 BAKERSFIELD CA 93380 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,330,293.84 9,120.00 2.a. Extra Work 26,880.21 35.67 b. Adjustment Comp. -19,904.59 -5,381.71 3. Materials on Hand 4. Earned Subject to Retention 4,337,269.46 3,773.96 5. Mobilization 6. Total Work Completed 4,337,269.46 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,337,269.46 3,773.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,773.96