Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-130-15-29 09-357504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 09-INY-127-22.7 ACST-S127(3) 09-INY-127-23.2 09-INY-127-29.3 Progress payment No. 007 Payment period ending: 04-19-18 HERBACK GENERAL ENGINEERING 2531 NOWLIN RD MINDEN NV 89423 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,644,536.55 0.00 2. a. Extra Work 77,297.30 0.00 b. Adustment Comp. 22,107.48 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,743,941.33 0.00 5. Mobilization 366,356.00 0.00 6. Total Work Completed 2,110,297.33 7. Deductions -10,000.00 147,480.90 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,100,297.33 147,480.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 147,480.90