Dept. of Trans. PROGRESS Serial No. Contract No. 14-233-08-26 09-359004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 49% 53% 09-INY-190-18.5/24.6 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-14 GRANITE CONSTRUCTION CO. P.O. BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,098,079.08 1,098,079.08 2.a. Extra Work b. Adjustment Comp. -18,765.25 -18,765.25 3. Materials on Hand 4. Earned Subject to Retention 1,079,313.83 1,079,313.83 5. Mobilization 6. Total Work Completed 1,079,313.83 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,079,313.83 1,079,313.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,079,313.83