Dept. of Trans. PROGRESS Serial No. Contract No. 21-020-14-19 09-363404 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 80% Location: Federal Project: 09-INY-178-43.4/43.4 NONE Progress payment No. 003 Payment period ending: 01-20-21 BOSCO CONSTRUCTORS INC 21353 MAYALL ST CHATSWORTH CA 91311 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 690,310.50 109,508.00 2. a. Extra Work b. Adustment Comp. 58,686.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 748,996.50 109,508.00 5. Mobilization 80,000.00 4,000.00 6. Total Work Completed 828,996.50 7. Deductions -147,338.40 -28,174.40 8. a. Contract Retentions b. Unsatisfactory Retentions -10,950.80 -10,950.80 c. Reduction after 95% Comp. 9. Total pay to Contractor 670,707.30 74,382.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 74,382.80