Dept. of Trans. PROGRESS Serial No. Contract No. 17-053-07-08 09-364304 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 0% Location: Federal Project: 09-MNO-395-106.3/118.7 NHP-P395 09-MNO-395-119.6/120.5 261-E Progress payment No. 001 Payment period ending: 02-17-17 ROAD & HIGHWAY BUILDERS LLC 96 GLEN CARRAN CIR #106 SPARKS NV 89431 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 99,238.33 99,238.33 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 99,238.33 99,238.33 5. Mobilization 6. Total Work Completed 99,238.33 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 99,238.33 99,238.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 99,238.33