Dept. of Trans. SEMI-FINAL Serial No. Contract No. 19-015-16-49 09-364604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 09-INY-6-4.3/8.4 HSNH-P006(12) Progress payment No. 006 Payment period ending: 08-31-18 GRIFFITH COMPANY 1128 CARRIER PKWY AV BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,672,569.48 8,810.45 2. a. Extra Work 42,690.25 10,192.95 b. Adustment Comp. 13,690.49 13,690.49 3. Materials on Hand 4. Earned Subject to Retention 2,728,950.22 32,693.89 5. Mobilization 203,456.00 0.00 6. Total Work Completed 2,932,406.22 7. Deductions -10,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,922,406.22 42,693.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 42,693.89