Dept. of Trans. PROGRESS Serial No. Contract No. 19-233-09-26 09-364704 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 47% Location: Federal Project: 09-MNO-395-60.0/69.9 SNHG-P395(274) Progress payment No. 002 Payment period ending: 08-20-19 CORAL CONSTRUCTION COMPANY PO BOX 347 WILSONVILLE OR 97070 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 633,285.00 396,035.00 2. a. Extra Work b. Adustment Comp. 8,170.00 8,170.00 3. Materials on Hand 4. Earned Subject to Retention 641,455.00 404,205.00 5. Mobilization 214,414.05 45,139.80 6. Total Work Completed 855,869.05 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 23,725.00 c. Reduction after 95% Comp. 9. Total pay to Contractor 855,869.05 473,069.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 473,069.80