Dept. of Trans. PROGRESS Serial No. Contract No. 24-292-14-10 09-366404 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 85% Location: Federal Project: 09-MNO-395-58.2/60.4 HSNH-P395(349) Progress payment No. 014 Payment period ending: 10-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,587,722.63 9,796.00 2. a. Extra Work 153,171.08 28,304.46 b. Adustment Comp. -7,564.22 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,733,329.49 38,100.46 5. Mobilization 171,120.00 0.00 6. Total Work Completed 6,904,449.49 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,894,449.49 28,100.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 28,100.46