Dept. of Trans. PROGRESS Serial No. Contract No. 24-325-11-09 09-366404 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 85% Location: Federal Project: 09-MNO-395-58.2/60.4 HSNH-P395(349) Progress payment No. 015 Payment period ending: 11-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,634,935.43 47,212.80 2. a. Extra Work 156,531.13 3,360.05 b. Adustment Comp. -7,564.22 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,783,902.34 50,572.85 5. Mobilization 171,120.00 0.00 6. Total Work Completed 6,955,022.34 7. Deductions -20,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,935,022.34 40,572.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 40,572.85