Dept. of Trans. PROGRESS Serial No. Contract No. 23-079-11-39 09-367204 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 87% Location: Federal Project: 09-KER-202-4.7/5.2 HSST-S202(6) Progress payment No. 006 Payment period ending: 03-20-23 EVERLEVEL HOLDINGS LLC 5877 PINE AVE #120 CHINO HILLS CA 91709 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 784,021.60 39,046.10 2. a. Extra Work b. Adustment Comp. 12,105.50 0.00 3. Materials on Hand 63,246.61 0.00 4. Earned Subject to Retention 859,373.71 39,046.10 5. Mobilization 6. Total Work Completed 796,127.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 859,373.71 39,046.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 39,046.10