Dept. of Trans. PROGRESS Serial No. Contract No. 24-109-17-03 09-367504 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 22% Location: Federal Project: 09-KER-5756-0.0/92.0 NONE Progress payment No. 009 Payment period ending: 04-20-24 BOWE CONTRACTORS INC 609 BAILEY CT TEHACHAPI CA 93561 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,421,008.16 1,020,630.62 2. a. Extra Work 31,897.83 3,805.04 b. Adustment Comp. -40.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,452,865.99 1,024,435.66 5. Mobilization 6. Total Work Completed 6,452,865.99 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,452,865.99 1,024,435.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,024,435.66