Dept. of Trans. PROGRESS Serial No. Contract No. 24-200-15-37 09-367504 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 31% Location: Federal Project: 09-KER-5756-0.0/92.0 NONE Progress payment No. 012 Payment period ending: 07-20-24 BOWE CONTRACTORS INC 609 BAILEY CT TEHACHAPI CA 93561 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,158,150.77 1,162,755.68 2. a. Extra Work 59,076.01 0.00 b. Adustment Comp. -40.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 10,217,186.78 1,162,755.68 5. Mobilization 6. Total Work Completed 10,217,186.78 7. Deductions -3,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,214,186.78 1,162,755.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,162,755.68