Dept. of Trans. PROGRESS Serial No. Contract No. 25-052-13-46 09-367504 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 42% Location: Federal Project: 09-KER-5756-0.0/92.0 NONE Progress payment No. 019 Payment period ending: 02-20-25 BOWE CONTRACTORS INC 609 BAILEY CT TEHACHAPI CA 93561 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,604,459.07 266,580.61 2. a. Extra Work 718,016.02 175,584.07 b. Adustment Comp. -444.60 0.00 3. Materials on Hand 4. Earned Subject to Retention 16,322,030.49 442,164.68 5. Mobilization 6. Total Work Completed 16,322,030.49 7. Deductions -10,507.50 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,311,522.99 442,164.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 442,164.68