Dept. of Trans. PROGRESS Serial No. Contract No. 24-327-09-22 09-368004 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 15% Location: Federal Project: 09-MNO-395-91.6/93.4 HSNH-P395(352) Progress payment No. 007 Payment period ending: 11-20-24 PAPICH CONSTRUCTION COMPANY INC 398 SUNRISE TERRACE ARROYO GRANDE CA 93420 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,947,423.67 40,904.10 2. a. Extra Work 124,835.36 22,297.63 b. Adustment Comp. -7,057.60 0.00 3. Materials on Hand 109,275.00 0.00 4. Earned Subject to Retention 11,174,476.43 63,201.73 5. Mobilization 540,000.00 0.00 6. Total Work Completed 11,605,201.43 7. Deductions -100,000.00 15,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,614,476.43 78,201.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 78,201.73