Dept. of Trans. PROGRESS Serial No. Contract No. 26-022-09-41 09-368004 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 57% Location: Federal Project: 09-MNO-395-91.6/93.4 HSNH-P395(352) Progress payment No. 021 Payment period ending: 01-20-26 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,370,001.90 13,694.70 2. a. Extra Work 762,264.86 0.00 b. Adustment Comp. 290,018.68 -7,121.65 3. Materials on Hand 4. Earned Subject to Retention 15,422,285.44 6,573.05 5. Mobilization 540,000.00 0.00 6. Total Work Completed 15,962,285.44 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,952,285.44 6,573.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,573.05