Dept. of Trans. PROGRESS Serial No. Contract No. 21-138-14-10 09-370104 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 15% Location: Federal Project: 09-INY-395-0.1/0.1 SNHG-X027(11) Progress payment No. 002 Payment period ending: 05-20-21 PTM GENERAL ENGINEERING SERVICES INC 5942 ACORN ST RIVERSIDE CA 92504 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 100,098.50 37,996.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 100,098.50 37,996.00 5. Mobilization 6. Total Work Completed 100,098.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 100,098.50 37,996.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 37,996.00