Dept. of Trans. PROGRESS Serial No. Contract No. 26-232-15-43 09-374504 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 39% Location: Federal Project: 09-INY-395-56.8/57.4 ACNH-P395(356) 09-INY-395-57.9/R58.3 Progress payment No. 003 Payment period ending: 08-21-26 CALIFORNIA HIGHWAY CONSTRUCTION GROUP INC 1647 WILLOW PASS RD #150 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,667,922.37 1,020,058.51 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 130,341.30 -37,165.41 4. Earned Subject to Retention 1,798,263.67 982,893.10 5. Mobilization 547,846.00 115,336.00 6. Total Work Completed 2,215,768.37 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,336,109.67 1,088,229.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,088,229.10