Dept. of Trans. PROGRESS Serial No. Contract No. 26-022-09-45 09-374704 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 50% Location: Federal Project: 09-INY-168-17.6/18.3 ACST-X027(12) 09-INY-395-114.9/117.8 Progress payment No. 008 Payment period ending: 01-15-26 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,309,298.19 1,036,568.31 2. a. Extra Work 320,976.77 1,836.57 b. Adustment Comp. -19,486.35 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,610,788.61 1,038,404.88 5. Mobilization 2,090,000.00 0.00 6. Total Work Completed 9,700,788.61 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,695,788.61 1,033,404.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,033,404.88