Dept. of Trans. PROGRESS Serial No. Contract No. 26-050-09-42 09-374704 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 56% Location: Federal Project: 09-INY-168-17.6/18.3 ACST-X027(12) 09-INY-395-114.9/117.8 Progress payment No. 009 Payment period ending: 02-15-26 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,967,103.80 657,805.61 2. a. Extra Work 667,723.41 346,746.64 b. Adustment Comp. -8,450.79 11,035.56 3. Materials on Hand 4. Earned Subject to Retention 8,626,376.42 1,015,587.81 5. Mobilization 2,090,000.00 0.00 6. Total Work Completed 10,716,376.42 7. Deductions -10,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,706,376.42 1,010,587.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,010,587.81