Dept. of Trans. PROGRESS Serial No. Contract No. 26-078-09-09 09-374704 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 51% Location: Federal Project: 09-INY-168-17.6/18.3 ACST-X027(12) 09-INY-395-114.9/117.8 Progress payment No. 010 Payment period ending: 03-15-26 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,705,977.06 1,738,873.26 2. a. Extra Work 696,957.28 29,233.87 b. Adustment Comp. -24,989.63 -16,538.84 3. Materials on Hand 4. Earned Subject to Retention 10,377,944.71 1,751,568.29 5. Mobilization 2,090,000.00 0.00 6. Total Work Completed 12,467,944.71 7. Deductions -20,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,447,944.71 1,741,568.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,741,568.29