Dept. of Trans. PROGRESS Serial No. Contract No. 24-352-10-17 09-375304 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 75% Location: Federal Project: 09-KER-58-80.5/81.0 NONE 09-KER-58-105.6/106.1 Progress payment No. 002 Payment period ending: 12-17-24 INTERSTATE CIVIL CONSTRUCTION PO BOX 2819 WRIGHTWOOD CA 92397 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 891,033.14 600,219.24 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 891,033.14 600,219.24 5. Mobilization 6. Total Work Completed 891,033.14 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 891,033.14 600,219.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 600,219.24