Dept. of Trans. PROGRESS Serial No. Contract No. 22-020-12-13 09-377304 PROGRESS PAYMENT VOUCHER %complete: %time: 55% 50% Location: Federal Project: 09-KER-14-16.6/16.6 NONE Progress payment No. 005 Payment period ending: 01-20-22 JAMES E. THOMPSON INC. 7001 MCDIVITT DR #B BAKERSFIELD CA 93313 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 452,591.52 86,781.11 2. a. Extra Work 8,317.00 0.00 b. Adustment Comp. -9,122.62 0.00 3. Materials on Hand 4. Earned Subject to Retention 451,785.90 86,781.11 5. Mobilization 6. Total Work Completed 451,785.90 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 441,785.90 76,781.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 76,781.11