Dept. of Trans. PROGRESS Serial No. Contract No. 22-049-15-13 09-377304 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 62% Location: Federal Project: 09-KER-14-16.6/16.6 NONE Progress payment No. 006 Payment period ending: 02-20-22 JAMES E. THOMPSON INC. 7001 MCDIVITT DR #B BAKERSFIELD CA 93313 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 507,822.70 55,231.18 2. a. Extra Work 25,286.48 16,969.48 b. Adustment Comp. -9,122.62 0.00 3. Materials on Hand 4. Earned Subject to Retention 523,986.56 72,200.66 5. Mobilization 6. Total Work Completed 523,986.56 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 523,986.56 82,200.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 82,200.66