Dept. of Trans. PROGRESS Serial No. Contract No. 22-080-17-06 09-377304 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 73% Location: Federal Project: 09-KER-14-16.6/16.6 NONE Progress payment No. 007 Payment period ending: 03-18-22 JAMES E. THOMPSON INC. 7001 MCDIVITT DR #B BAKERSFIELD CA 93313 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 622,846.64 115,023.93 2. a. Extra Work 38,254.48 12,968.00 b. Adustment Comp. -12,827.15 -3,704.53 3. Materials on Hand 4. Earned Subject to Retention 648,273.97 124,287.40 5. Mobilization 6. Total Work Completed 648,273.97 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 648,273.97 124,287.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 124,287.40