Dept. of Trans. PROGRESS Serial No. Contract No. 22-110-17-12 09-377304 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 81% Location: Federal Project: 09-KER-14-16.6/16.6 NONE Progress payment No. 008 Payment period ending: 04-20-22 JAMES E. THOMPSON INC. 7001 MCDIVITT DR #B BAKERSFIELD CA 93313 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 724,903.95 102,057.31 2. a. Extra Work 41,037.48 2,783.00 b. Adustment Comp. -12,827.15 0.00 3. Materials on Hand 4. Earned Subject to Retention 753,114.28 104,840.31 5. Mobilization 6. Total Work Completed 753,114.28 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 748,114.28 99,840.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 99,840.31