Dept. of Trans. PROGRESS Serial No. Contract No. 23-206-07-32 09-377704 PROGRESS PAYMENT VOUCHER %complete: %time: 15% 38% Location: Federal Project: 09-MNO-395-34.1/34.1 NONE Progress payment No. 002 Payment period ending: 07-20-23 SAN PATRICIO CONSTRUCTION INC 4820 S ESCALON BELLOTA RD FARMINGTON CA 95230 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 127,756.30 122,732.30 2. a. Extra Work 10,500.00 10,500.00 b. Adustment Comp. 3. Materials on Hand 40,193.00 17,879.00 4. Earned Subject to Retention 178,449.30 151,111.30 5. Mobilization 44,325.00 44,325.00 6. Total Work Completed 182,581.30 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 222,774.30 195,436.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 195,436.30