Dept. of Trans. PROGRESS Serial No. Contract No. 23-284-08-11 09-377704 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 79% Location: Federal Project: 09-MNO-395-34.1/34.1 NONE Progress payment No. 005 Payment period ending: 10-13-23 SAN PATRICIO CONSTRUCTION INC 4820 S ESCALON BELLOTA RD FARMINGTON CA 95230 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 637,851.60 258,114.80 2. a. Extra Work 37,955.00 27,455.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 675,806.60 285,569.80 5. Mobilization 59,100.00 2,955.00 6. Total Work Completed 734,906.60 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions -28,556.98 -28,556.98 c. Reduction after 95% Comp. 9. Total pay to Contractor 696,349.62 259,967.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 259,967.82