Dept. of Trans. SEMI-FINAL Serial No. Contract No. 24-151-16-03 09-378704 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 09-MNO-395-55.5/58.2 NONE Progress payment No. 009 Payment period ending: 11-27-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,903,949.60 0.00 2. a. Extra Work 245,093.16 203,040.30 b. Adustment Comp. -136,139.42 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,012,903.34 203,040.30 5. Mobilization 600,000.00 0.00 6. Total Work Completed 6,612,903.34 7. Deductions -40,000.00 -30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,572,903.34 173,040.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 173,040.30