Dept. of Trans. PROGRESS Serial No. Contract No. 25-204-13-19 09-378804 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 64% Location: Federal Project: 09-MNO-395-R9.8/R12.6 ACNH-P395(353) Progress payment No. 003 Payment period ending: 07-20-25 HAT CREEK CONSTRUCTION & MATERIALS INC 24339 STATE HWY 89 N BURNEY CA 96013 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,628,391.89 6,701,315.41 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 9,628,391.89 6,701,315.41 5. Mobilization 1,300,000.00 65,000.00 6. Total Work Completed 10,928,391.89 7. Deductions -15,000.00 -15,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,913,391.89 6,751,315.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,751,315.41