Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 23-249-16-06 09-378904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 09-KER-14-46.2/52.8 NONE Progress payment No. 005 Payment period ending: 08-22-23 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,415,965.78 6,729.25 2. a. Extra Work b. Adustment Comp. -111,738.88 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,304,226.90 6,729.25 5. Mobilization 375,000.00 0.00 6. Total Work Completed 6,679,226.90 7. Deductions -129,298.45 -50,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,549,928.45 -43,270.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -43,270.75