Dept. of Trans. PROGRESS Serial No. Contract No. 25-261-13-52 09-379104 PROGRESS PAYMENT VOUCHER %complete: %time: 58% 37% Location: Federal Project: 09-INY-395-91.6/100.8 ACNH-P395(354) Progress payment No. 004 Payment period ending: 09-16-25 ROAD & HIGHWAY BUILDERS LLC PO BOX 70846 RENO NV 89570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,490,805.76 4,616,506.97 2. a. Extra Work 7,800.00 7,800.00 b. Adustment Comp. 205,410.00 205,410.00 3. Materials on Hand 4. Earned Subject to Retention 14,704,015.76 4,829,716.97 5. Mobilization 2,804,858.00 140,242.90 6. Total Work Completed 17,508,873.76 7. Deductions -12,925.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,495,948.76 4,964,959.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,964,959.87