Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 23-260-09-57 09-379304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 09-INY-127-21.0/34.5 CSTP-P127(3) 09-INY-127-41.8/49.4 Progress payment No. 006 Payment period ending: 08-21-23 HAT CREEK CONSTRUCTION & MATERIALS INC 24339 STATE HWY 89 N BURNEY CA 96013 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,770,004.34 98,336.67 2. a. Extra Work 274,653.13 127,971.13 b. Adustment Comp. -175,696.19 -175,696.19 3. Materials on Hand 4. Earned Subject to Retention 14,868,961.28 50,611.61 5. Mobilization 650,000.00 0.00 6. Total Work Completed 15,518,961.28 7. Deductions -15,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,503,961.28 40,611.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 40,611.61