Dept. of Trans. PROGRESS Serial No. Contract No. 24-354-09-18 09-379504 PROGRESS PAYMENT VOUCHER %complete: %time: 37% 14% Location: Federal Project: 09-INY-5709-0.0 NONE Progress payment No. 002 Payment period ending: 12-18-24 FEC FUTURE CONTRACTORS AND ENGINEERS INC 184 TECHNOLOGY DRIVE #205 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,664,004.76 1,125,213.76 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -71,221.22 4. Earned Subject to Retention 1,664,004.76 1,053,992.54 5. Mobilization 6. Total Work Completed 1,664,004.76 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,664,004.76 1,053,992.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,053,992.54