Dept. of Trans. PROGRESS Serial No. Contract No. 20-233-09-47 09-380804 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 100% Location: Federal Project: 09-MNO-395-12.6/35.4 ACNH-P395(279) Progress payment No. 002 Payment period ending: 08-18-20 AMERICAN PAVEMENT SYSTEMS INC 1012 11TH ST #1000 MODESTO CA 95354 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,933,508.78 1,453,570.68 2. a. Extra Work 25,532.28 25,532.28 b. Adustment Comp. -3,447.26 -3,447.26 3. Materials on Hand 4. Earned Subject to Retention 1,955,593.80 1,475,655.70 5. Mobilization 6. Total Work Completed 1,955,593.80 7. Deductions -20,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,935,593.80 1,455,655.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,455,655.70